Dredging is critical
to manage sediment shoaling and maintaining the navigability of our waterways
and to protecting the commercial and recreational benefits that they provide. The disposal and management of dredged
material have been debated for years, especially within the communities that thrive
along these water bodies. Some of the
routine issues of concern are: scope and
extent of dredging, dredged material management strategy, impacts to the local
community including economic and aesthetic impacts, and potential risks to the
local environment.
Clean Ocean
Action (COA) believes that dredged material can be a valuable resource, reused for beneficial purposes if and when it meets criteria that helps protect
the environment. COA also believes that
community awareness and involvement are vital for implementing suitable
beneficial reuse alternatives using dredged materials. For more than three decades, COA has actively
reviewed dredged material management solutions in the NJ-NY area and continues
to advocate for identifying and implementing options for beneficial reuse of
dredged materials. COA monitors various
dredging projects occurring in the region and engages and promotes awareness
among the communities.
COA has been
following maintenance dredging projects in the state of New Jersey and sharing
updates regularly through various platforms (website, blog, newsletter, social
media etc.) including the recent maintenance dredging in the Shrewsbury River
in New Jersey. The New Jersey Department
of Transportation (NJDOT) recently began sand shoal maintenance dredging in
three state navigation channels on the Shrewsbury River in Monmouth County, NJ.
This is the first part of a two-phase project on the Shrewsbury River under
NJDOT’s State Channel Dredging Program that was started to address the impacts
from Superstorm Sandy. According to the
permit, approximately 17,500 cubic yards of dredged material with more than 90% sand
will be removed using hydraulic dredging from selected cores in three channels
of the river in Monmouth County, which are listed below. The dredged material will be used for beach
placement, which is a beneficial reuse that COA supports under the right conditions. Dredged material
which meets the greater than 90% sand criteria as per NJ’s dredge material management
guidelines will be transported through pipelines and used as beach fill for
beach replenishment nourishment along the eroded shoreline of Monmouth
Beach. For this project, the sand will
be placed in front of the existing dune between Central and Park Road.
The Shrewsbuy
river maintenance dredging officially began on October 23, 2017, and as per
permit conditions was scheduled to be completed on Dec 31, 2017. At the time of completing this report, COA is
awaiting confirmation from DOT about the status update on this project.
The following
three channels were dredged under this project:
· Monmouth Beach channel (#016) in the boroughs of
Monmouth Beach and Sea Bright – max. depth 6 ft. below the plane of mean low
water level (MLW)
· Rumson Country Club Y channel (#017) in the
boroughs of Rumson and Sea Bright - 5 ft. MLW
· Oceanport Creek entry channel (#025) in the borough
of Oceanport – 4 ft. MLW
COA was granted permission from NJDOT and NJDEP to visit the dredging site with a few staff and
local stakeholders for a firsthand experience of the various stages under this
project, which can be used to inform the local community. On Dec 18, 2017, COA staff Cindy Zipf
(Executive Director), Alison McCarthy (Coastal Watershed Protection
Coordinator), and Dr. Swarna Muthukrishnan (Staff Scientist) visited the NJDOT
field office in Monmouth Beach to meet personnel and view the dredging/beach
replenishment activity. They were joined
by Dave Stickle (Monmouth Beach Councilman) and Brian Williams (Monmouth Beach
Environmental Commission). Bill
Henderson and Sherif Ismail, engineers from the Office of Maritime Resources in
NJDOT organized the visit for COA. The
dredging contractor Tristate Environmental was represented by their site
supervisor Wayne. As part of the
dredging team, Audrey from JBA consulting who is the field inspector onsite was
also present during the visit. Together
they offered COA’s team a tour around the dredging location and explained the
various processes involved in the dredging and beach replenishment.
At the time
of our visit, the dredging was already completed in channel #016, and dredging
of #017 was in progress. The actual
dredging operation runs for 12 hours every day on a 5-day schedule typically,
and a 1-3 member crew from TriState Environmental is in attendance to monitor
the dredging and to make sure that all activities proceed smoothly. The pipes that carry the dredged material to
the booster pump located in-river in Monmouth Beach are sunk and weighted in
the bottom of the river. The booster
pump is sited to ensure that the heavy sand-slurry that is dredged from the
river can be transported to the dewatering zone on the beach, which is located
across the road. As the dredged
material is pumped into the dewatering zone continuously, a trash trap removes any
debris that is transported with the dredged material. Once in the dewatering zone, the slurry material
starts to dry up, which typically is a few days (1-3). As the continuous flow of slurry dries, the
clearer water flows to the ocean, and the sand, which is in different stages of
drying appear in various shades of grey initially. This should not be of concern as these
materials have been dredged from a few feet below the MLW that are not exposed
to direct sunlight. As per NJ monitoring
requirements for dredge material beach replenishment activity, the dried sand
materials are routinely visually inspected by NJDOT and the project personnel
to ensure they meet greater than 90% sand criteria. Periodically, the dewatered, dried
sand material is hauled up and spread on the beach as beach fill in the
designated location. These dredged materials, once dewatered, subsequently
lighten due to bleaching from sunlight. Once
the maintenance dredging activity is completed and the sand completely dries,
the beach replenishment activity will be completed.
According to NJDOT and Tristate Environmental, daily maintenance activities include cleaning and flushing the pipelines after dredging every day. The trash trap in the dewatering zone is also removed and cleaned every day. The following photos show the various stages of sludge dewatering and beach replenishment that is part of this maintenance dredging project. (i) dewatering zone with the trash trap (ii) sand in varying stages of drying and color (iii) flow of clearer water towards the ocean (iv) beach replenishment using the dewatered sludge with greater than 90% sand.
II- sludge with greater than 90% sand in various
stages of drying
|
I - sludge dewatering zone with trash trap |
III-sludge
dewatering zone (incl. trash trap and hauler)
|
No comments:
Post a Comment